| N-50 & Cornhusker Road Intersection Modification Project Contacts: Carl Humphrey, NDOR Urban & Lighting Engineer, 402.479.3842 Information Posted March 2009
Proposed Construction: The proposed improvements at the N-50/Cornhusker Intersection and N-50/Meadows Parkway intrersection include channelizing the westbound Cornhusker Road approach to N-50, a raised median and geometric modifications to limit left turns from the North-South frontage road just east of the intersection. The improvements to Meadows Parkway intersection include pavement widening and geometric modifications to facilitate traffic turning off N-50 onto the frontage road. Lighting/Signals: Cornhusker intersection is already signalized and roadway lighting may need to be adjusted. Right of Way: Acquisition of new right-of-way will be minor. Phasing: Project to be built under traffic. No detour is required. Schedule: The project is currently scheduled for a 7/30/2009 letting Cost: The project is estimated to cost $100,000. (2009 dollars).
|
||