c
Official State of Nebraska Web Site

 




 

Regular Acrobat Reader Download
Help with PDF's for those with visual disabilities


 

US 77- Platte River Bridge
South of Fremont
Project # NH-BR-77-3(128)
Control #
22265
Text Only

Find out more about automatic updates before you subscribe Click to subscribe to automatic updates from NDOR whenever this page changes

If you have questions about this project,
 you may call the NDOR District 2 Office at 
402-595-2534,
 or use the “Ask a Question” link on the main page of the NDOR website

Info Current as of December 6, 2010

Project FAQ's

Additional Documents

Environmental Assessment
(Final-Finding of No Significant Impact)

Environmental Assessment
(Draft)

Large Docs - Please allow time to download

Fact Sheet from Hearing, Location Map & Aerial Mosaic

In English | In Spanish
updated June 2010

Updated 12-6-10

Proposed Construction

This project will include the construction of a new four-lane bridge on US-77 over the Platte River, south of Fremont.  Also included will be the construction of approximately 4,500+/- feet of new roadway.  

The removal of the existing bridge will be completed after traffic has been moved onto the new structure.

Related Studies

The Draft Environmental Assessment is posted above. A Draft "Bridge Replacement Options" report is also available by contacting Micky Jacobs (above).

Right of Way

To accommodate construction, an additional 0.50 acres of right-of-way, including a mobile home, has been acquired from one parcel.  Relocation of the mobile home, located northeast of the proposed bridge, has been completed.  Also, 0.98 acres of temporary constructions easements has been acquired.

Environmental Impact

Right of way - 0.5 acre acquisition and one relocation, 0.98 acre of temporary easement; local community and traffic disruption during construction; Monnich Park reconstruction of the driveway; Utilities will require adjustments; 0.27 acres of wetlands will be impacted; Soil will be disturbed by construction activities; threatened and endangered species may be affected.

Phasing

US-77 traffic will be maintained on the existing bridge or the new bridge during construction.  During daylight hours, each direction of traffic may be restricted to one-lane traffic with appropriate traffic control.  Temporary surfacing may be built to accommodate US-77 traffic at certain times and to maintain access at all times during construction.

Schedule

The project was let to contract on Oct. 21, 2010, with construction to begin later in 2010.  It is expected to take approximately two years to complete the construction of the new bridge and approach roadways, and another two years to complete the removal of the existing bridge and approach roadways.