| January
- February 2004 |
|||
|
February 2004 preparing to install Sheet Piling west of Burke Boulevard |
February 2004 installing Sheet Piling for High Voltage Transmission Line west of Burke Boulevard |
February 2004 installing Sheet Piling for High Voltage Transmission Line west of Burke Boulevard |
February 2004 installing Sheet Piling along Whitehall Condominiums west of Burke Boulevard |
|
January 2004 insulating concrete retaining wall along the South Frontage Road east of Burke Boulevard |
January 2004 heating and insulating concrete retaining wall along the South Frontage Road east of Burke Boulevard |
January 2004 placing project cam pole north of West Dodge Road and east of 108th Avenue |
January 2004 future project cam view north of West Dodge Road and east of 108th Avenue looking west |
|
Rich Zelensky Highway
Project Manager |
|||